Topbond PLC Group > Bignold Road Bridge
Topbond Group PLC

Today is: 13/10/2008
  Homepage - Rail - Bignold Road Bridge

Project: Refurbishment of railway bridge in East London

Bignold Road Bridge Bignold Road Bridge
Click on thumbnails for a larger view
Bignold Road Bridge is a 23.5m single span underbridge carrying non electrified railway lines over Bignold Road in East London. As part of the East Anglian framework agreement, Topbond were asked to replace the existing load bearing abutment arrangement with a new concrete-encased steel beam arrangement.

Topbond carried-out the following works:

Excavation and casting of temporary bridge deck-prop
R/C foundations at four locations, done sequentially to
prevent the risk of abutment movement.

Removal of 1 No. brick pilaster and subsequent
rebuilding with original bricks and caps.

Temporary propping of the bridge adjacent to the
abutment (outside rail possessions).

Jacking the bridge sequentially as work progressed to
remove concrete bedstone and brickwork to the designed
levels then place and fix steel grillage and bearings.
No jacking loads were applied except during rail
possessions (5 No.). Steel beams were blocked and tied
to prevent movement. The alignment and level of the
bridge was monitored and recorded throughout.

Removing the existing stone and concrete bed stones and
brickwork sequentially to the required level.

Installing prefabricated steel trellis in sections at
bridge bearing locations.

Fixing steel reinforcement to steel trellis, formwork
fixing and concrete pumping in to form a new R/C cill
beam.

Finally, steelwork repainting and abutment wall
brickwork repairs were carried out as required.